Filled indentations, holes, and pit holes with flox and micro balloon resin mix.
In October of 2011, I purchased a Vans RV-8 "QuickBuild" experimental aircraft kit. This blog serves as my builders log and captures the major portions of the build process.
Tuesday, February 20, 2018
Monday, February 19, 2018
Canopy Skirt
As anticipated, the canopy skirt has taken a significant number of hours to complete. Trying to get this phase completed during the winter months hampered our progress. Epoxy resin's don't do well in sub-freezing temperatures.
We started with the VANS stock molded piece of fiberglass. The U shaped part that's shipped from the factory needed to be highly customized in order to properly fit the fuselage and canopy. This involved splitting the part in two and re-fabricating a large portion of the rear section.
We started with the VANS stock molded piece of fiberglass. The U shaped part that's shipped from the factory needed to be highly customized in order to properly fit the fuselage and canopy. This involved splitting the part in two and re-fabricating a large portion of the rear section.
![]() |
| Nylon tape was applied as a release film on the aircraft fuselage skin and canopy. Multiple layers of glass were applied to the upper surface of the canopy skirt. |
![]() |
| The two skirt halves were joined by reinforcing the back with pieces of insulating foam. Fiberglass wet layup was applied over the foam pieces. |
![]() |
| Rough finish after the wet layup joining of the two skirt halves. |
![]() |
| Skirt joined and ready for finishing fills and LOTS of sanding. |
Sunday, June 5, 2016
Instrument Panels ~ Final Finishing
![]() |
| Back side of cured part for side panels. |
Vacuum bagging of the instrument side panel material was a success however the part compressed more than we thought it would so we didn't achieve the desired thickness necessary to surface match to the center panel. That's ok. A small lip down from the center panel to the side panels still works. One would think 8 layers of cloth would make for a thick part. Eight hours of -28InHg vacuum really bleeds all excess resin resulting in a very nice 50:50 fabric to resin ratio for the part.


Left and right side panels were cut to exactly match the aluminum back plate. This required a lot of careful cut, fit, sand, repeat. The holes for the AOA, ELT, and side vents will be cut after clear coating.
![]() |

Center and side panels were scuff and cleaned. Wax & Grease remover was used as a final cleaner to ensure that all contaminants were removed prior to painting.
Master painter, John Branchaw, carefully applied four layers of clear coat to each panel.
![]() |
| Finished carbon fiber panel. |
Next step, mount the avionics trays and install the avionics.
Wednesday, June 1, 2016
Instrument Side Panels - vacuum bagging
Finish sanded layer of SuperFill that was applied to panel mold. Waxed mold and misted a few coats of mold release.
Our goal is to surface match the side panels to the center panel. This requires a material buildup to equal the thickness of the center aluminum piece plus the carbon fiber overlay. A quick calculation determined that we would need six layers of fiberglass plus two layers of carbon fiber. A 50:50 resin to fabric ratio requires 128g of resin. That's a lot!
Eight hours later... Removing the bagging material and bleeder-breather layers revealed a very tacky part that had clearly not yet finished curing under room temperature and good vacuum.
We'll leave the part exposed to a strong morning sun for a few hours to finish the cure process.
Tuesday, May 31, 2016
Wing tip - inside plug fabrication
Used 88g of liquid urethane expanding foam poured onto release play lining wingtip inside surface. The 15x expansion created a good size plug. Next step, fiberglass wet layup using the plug to press the glass to the wingtip surface. We may even vacuum bag the plug to the surface so as to minimize epoxy weight and maximize adhesion.
![]() |
| Fabricated wing tip mold plug. |
Instrument Panel - composite sides
Sanded mold for side panel pieces. Applied a layer of SuperFill. Will be ready to sand and start vacuum bagging this evening.
Tuesday, January 12, 2016
Avionics wire cleanup
Wednesday, November 5, 2014
Sunday, May 4, 2014
Beringer Brake System
Installed the brake fluid reservoir to the firewall assembly. Fabricated the left and right brake lines and installed them to the brake line fittings. Installed the brake hoses.
Tuesday, April 1, 2014
Spring is here ;-) Tail wheel mount, Control, CHT & EGT Wiring Connections
Finally the WX broke so Mike and I were able to work on
the plane again. We've both agreed
that the plane will be done by Oshkosh (just not sure which one but we aren't
telling anyone that part when they ask which one).
Davin and I worked on finishing up installation of the beautifully chromed tail wheel mount assembly. Installed the tail wheel spring mount. Reluctantly had to add six CS 4-4 pop rivets to the bottom of the rear bulkhead due to space constraints.
Mike mounted the control cables. We also finished up the CHT and EGT wiring connections.
| Davin Squeezing Rivets |
| Wheel Mount Assembly |
| Aft Bulkhead |
| Prop Governor Linkage |
| Lower battery bus |
Mike mounted the control cables. We also finished up the CHT and EGT wiring connections.
Thursday, January 30, 2014
Can it get any colder??? Ran Control Cables
Too
cold!
Ran the three control cables from the quadrant to the engine. Will need to order a longer one for the throttle
Ran the three control cables from the quadrant to the engine. Will need to order a longer one for the throttle
METAR KGAI 010155Z AUTO 14003KT 10SM CLR 00/M09 A3023
Monday, December 23, 2013
More Cold WX! Drilled Hole for Control Cables
Mike came out to the factory and
didn't get much done....too cold.
Drilled the holes in left gear tower for the control cables to pass
through. Didn't have the right size snap
grommets so they'll need to be ordered.
Tuesday, December 10, 2013
Cold Day in the Factory! ... More Wiring
Starting to get really cold in
the factory. Did some cleanup and
dragged Mikes blast heater over from his hangar.
Mike pulled apart all the wiring run
attachments behind the panel. With the
new GRT Mini AP taking the place of the originally planned TruTrak Gemini some
rewiring will need to happen. Arjan Plomp agreed to help out going through John Stark's disastrous wiring job to re-do a lot of the rewiring.
Saturday, December 7, 2013
Running Wires
Mike Regen routed all the wires from the firewall to their respective attach points. Attached a bunch of cushion clamps for the
wire runs. Started on the connections
for the CHT and EGT wires.
Inside the cockpit, I installed the GRT autopilot servos that have replaced the TruTrak servos.
Inside the cockpit, I installed the GRT autopilot servos that have replaced the TruTrak servos.
Saturday, November 23, 2013
Tail Wheel Mount & Engine Sensors
Started working on installation of the beautifully chromed tail wheel mount. Space Coast Plating did a great job of chroming the mount.
The rear bulkhead was
removed to get it installed and mounted correctly.
Mike Regen started attaching the engine sensors. All the EGT and CHT sensors were attached
along with the oil temperature sensor.
The starter will need to be replaced with a shorter
SkyTec....bummer. The B&C starter is
a much better unit.
METAR KGAI 240155Z AUTO 31012G18KT 290V350 4SM SCT018 BKN026 OVC037 00/M04 A3017 RMK AO1=
Sunday, November 17, 2013
ENGINE MOUNTING DAY!
ENGINE
MOUNTING DAY! Bill Hughes (A&P/IA)
was kind enough to come over and lend a hand mounting the engine. We had some trouble getting it maneuvered
into the mount then getting the alignment correct to get the mounting bolts in
properly. After some choice words of
encouragement (aimed at the engine) we had it mounted in about an hour.
![]() |
| Engine and Mounts Ready |
Saturday, November 16, 2013
Engine Accessory Installation
- Attempted to mount the starter but the B&C starter will not fit with the fuel injection servo. Need to do some research on fitment.
- Mounted fuel hose between fuel pump and fuel servo.
- Mounted oil in and out lines for oil cooler.
- Removed magneto studs and attached new shorter studs for the P-Mags.
- Mounted P-Mags.
- Mounted the fuel injection servo.
![]() |
| Fuel Injection Servo Linkage |
Wednesday, November 13, 2013
Prep for Engine Mounting
Started prepping engine for
mounting. Mounted primary and back-up
alternators. Mounted propeller governor
and re-clocked control cable arm. P-Mags
will require shorter studs than the original impulse magnetos so determined
correct size and will order them.
Mounted control cable mounts and mixture arm to engine.
Tuesday, November 12, 2013
Firewall Mounts
Mounted heater valve on firewall. Attached fuel sensor hose to FW. Fabricated and mounted mount for fuel flow
transducer and mounted with hoses.
Attached engine mount to FW.
Monday, November 11, 2013
Firewall Pass-Throughs
Finished drilling holes in
firewall for pass-throughs. Mounted
control cable eyeballs and drilled out inserts to match control cable
diameter. Mounted alternator regulator
and starter relay.
Subscribe to:
Posts (Atom)


















